Saratoga County Waste Water Treatment

Description of Work:

The work performed at this project involved upgrades to the existing primary substation (replacing both substation transformers), new duct banks and manholes for new plant upgrades, new medium voltage switches and transfoRmers, power guard energy saving devices, two new diesel generators and associated switches, conduit and conductors in classified and non classified areas for plant upgrades, replace and add new motor control centers throughout the facility. Complete wiring of new UV system. All work was completed with the existing facility remaining in full operation throughout the project.

Saratoga County Water Treatment Plant

Description of Work:

The work performed on this project was an entire new facility consisting of seven buildings at two sites. Gross Electric, Inc. installed and designed seismic foundations & buildings for electrical substations, transformers, and generator pads. Installation of multiple 15KV substations. Distribution and instrumentation concrete duct banks & manholes (site wide). 1500 KW generators, paralleling gear, and ATS switches. Multiple motor control centers and large variable frequency drives. Seismic cable tray systems (all buildings). Power distribution and instrumentation conduit, cabling & terminations for all buildings and equipment, including pumping stations, storage tanks, chemical feed systems, pall filter rack systems. Complete token ring fiber networked fire alarm system, card access, CCTV & monitoring system, along with the remote monitoring & solar powered security system.

United States Postal Service- Karner Rd. Albany, NY

Description of Work:

The work performed at this project involved constructing a 2600 SF vault to house new high voltage substation, interior space demolition and renovations, site work, demolition of the facility’s medium voltage switchgear, outdoor pad mounted transformers, duct bank installation, retrofit/replacement of all of the facilities Federal Pacific electric panel boards and transformers, standby power system (less generator), related distribution equipment, and branch wiring to lighting fixtures, and power and lighting general space requirements, plumbing, gas piping, HVAC equipment installation and modification, fire suppression and alarm system modifications.

Beech-Nut Nutrition Corporation

Description of Work:

The work on this project consisted of installing conduit, wire, and motor control centers throughout the new facility. We also installed all conduit and wiring for power to the equipment, interconnect wiring and controls for multiple manufacturing lines. The work consisted of all types of wiring and conduit methods from EMT and rigid to most of the manufacturing being stainless steel conduit and fittings. The total project was completed with a majority of the work having to be finished in 3 months.

Global Foundries – Administrative Building

Description of Work:

The work on this project involved installing power distribution, branch circuits, lighting, and cable tray systems for a new office administration facility. This is a very fast track schedule consisting of a project manager, general foreman, five foreman, safety director and 40 electricians. We are also managing several other smaller contracts at the main chip Fab Plant facility for M&W Products China division installing all of their variable frequency drives, feeder conduits & motor terminations, etc.

Irving Tissue

Description of Work:

Gross Electric, Inc. has performed multiple jobs over the past few years. We have performed work from general maintenance to new building electrical systems to include power distribution, lighting, fire alarm, phone and fiber installation, to complete machine installs. Many of the projects were done with tight schedules working with multiple trades, multiple shifts, and seven days a week.

Lehigh Hanson Cement Plant

Description of Work:

The work performed at this facility consists of anything from daily maintenance work, equipment installation, 4160v cabling, high yard work, complete re feed and automation of entire facility.

Brookfield Power

Description of Work:

The work consists of work at multiple hydro plants. Maintenance, equipment upgrades, repairs, 1000 MCM 35kv cabling and terminations, dam repairs and upgrades.

Man working