LAFARGE/HOLCIM PYROLINE EXPANSION • RAVENA, NY

Expansion of cement plant capacity with an entire new production line. Installation included six MV primary substations feeding various parts of the plant, installation of all controls, lighting, communications, branch wire and feeders.  Initial contract completed in 12 months, with residual work continuing during plant commissioning. 180,000-man hours worked with no lost time injuries.

     
    LEHIGH HANSON CEMENT PLANT • GLEN FALLS, NY

    The work performed at this facility consists of anything from daily maintenance work, equipment installation, 4160V cabling, high yard work, complete re feed and automation of entire facility.

       

      Other projects we have worked on in this sector include but are not limited to:

      • GF Cement Cooler Mill
      • Essroc Cement
      • Jersen- Lafarge
      • FPI at Lafarge- Cooling Tower
      • Norlite – Power Distribution